Earned Value Management Basics

A silent, step-by-step introduction to earned value: PV, EV, AC, variances, SPI, CPI and forecasting with an illustrative example.

Free

Free 2-minute video lesson. A silent, step-by-step introduction to earned value: PV, EV, AC, variances, SPI, CPI and forecasting with an illustrative example. Short, visual and to the point, so you can watch it between meetings and apply it the same day.

Earned Value Management tells you whether a project is ahead or behind and over or under budget, using one consistent method. This silent video introduces the three core measures (planned value, earned value and actual cost), the schedule and cost variances, and the SPI and CPI indices. An illustrative worked example shows the math step by step, followed by a simple estimate at completion formula and tips for using EVM in real status reports. Useful for PMP candidates, project managers and PMO analysts.

What you'll learn

  • Why earned value?
  • Three core measures
  • Two variances
  • Two indices
  • Illustrative example: setup
  • Work it out
  • Forecast the finish
  • Other useful forecasts
  • Use EVM on your project
  • Practical tips
  • Key takeaway

Who it's for

Project and program managers, PMP candidates, PMOs and delivery leads.

Go deeper

Pair this lesson with the related free e-books and templates in the resource library, and read the latest practical articles on the blog.

Lesson notes (text version of the video)

Why earned value?: Spend alone misleads. Spending half the budget says nothing about finishing half the work.

Three core measures

  • Planned Value (PV): budgeted cost of work scheduled to date
  • Earned Value (EV): budgeted cost of work actually completed
  • Actual Cost (AC): what the completed work really cost
  • Budget at Completion (BAC): total approved budget

Two variances

  • Schedule variance: SV = EV - PV; Negative means behind schedule
  • Cost variance: CV = EV - AC; Negative means over budget

Two indices

  • SPI: SPI = EV / PV; Below 1.0: behind schedule
  • CPI: CPI = EV / AC; Below 1.0: over budget

Illustrative example: setup

  • BAC = 100,000
  • By month 3, planned work worth 40,000
  • Completed work worth 30,000
  • Actual cost so far: 36,000

Work it out

  1. PV = 40,000; EV = 30,000; AC = 36,000
  2. SV = 30,000 - 40,000 = -10,000
  3. CV = 30,000 - 36,000 = -6,000
  4. SPI = 0.75: behind schedule
  5. CPI = 0.83: over budget

Forecast the finish: EAC = BAC / CPI. Illustrative: 100,000 / 0.83 is roughly 120,000 if efficiency stays the same.

Other useful forecasts

  • ETC = EAC - AC: cost still to come
  • VAC = BAC - EAC: expected overrun or saving
  • TCPI: efficiency needed to finish on budget
  • Choose formulas that match why variance happened

Use EVM on your project

  1. Build a baseline with budgeted work packages
  2. Agree rules for earning progress
  3. Collect actual cost per period
  4. Report SPI and CPI trends monthly

Practical tips

  • Use 0/100 or 50/50 rules for short tasks
  • Watch trends, not a single month
  • Pair numbers with a short explanation
  • Rebaseline only through formal change control

Key takeaway: Earned value compares work done with plan and cost. Below 1.0 on SPI or CPI is an early warning.